Thank you for your patience and your presence wherever we've gathered as the church. We planned to be out of the building for one week. It has turned into about three, because the water issue in the back of the church building needs to be fixed at the foundation, and we want to fix it the right way. Here's where things stand and what's ahead.

Where the Church Will Be Gathering

Work Performed To Date

Week 1 (11/10 - 11/13): Demolition of Existing Floor Tiles, Cabinets, and Bathrooms

The Contractor teamed up with some of our church members and Teen Challenge to remove the existing floor tiles, cabinetry in the offices, and demolish both the men's and women's bathrooms so renovation can start from a clean slate. It was important to expose the existing condition of the concrete floors. Contractor began floor preparation by light sanding.

Week 2 (11/16 - 11/20): Assess Water Damage, Remove and Replace the Existing Plumbing

During demolition, the Contractor identified water damage in nursery, bathrooms, worship office, finance office, and pastor's office, caused by heavy leaking from the back of the church. Work could not continue per plan due to the potential for ongoing damage if the leak was not resolved. The board decided the best course of action was to perform a proper fix by trenching behind the church to expose the foundation of the building and installing a proper water barrier. While waiting for the insurance company to respond, the Contractor continued with removing and replacing the existing plumbing in the bathrooms.

Week 3 (11/23 - 11/27): Backfill and Pour Concrete, Grind Existing Concrete Floor, and Trench Church Rear

The Contractor finished backfill work and poured the new concrete in the trenches. Contractor began heavy grinding and sanding in preparation for the concrete seal scheduled next week. The Contractor also began trenching the exterior rear of the church building in preparation of water barrier installation.

Upcoming Work

Week 4 (11/30 - 12/4): Seal the Concrete Floor, Install Dry Wall, and Restore Fellowship Hall Furniture

Next week, the Contractor is scheduled to finish preparation of the foundation and begin installation of the epoxy floor sealant. After the sealant cures, the volunteers will restore the furniture in the Fellowship Hall and clean up the Sanctuary in preparation for a return to services in the building.

Week 5 (12/7 - 12/11): Exterior Water Barrier Installation and Continue Bathroom Renovations

The Contractor is scheduled to continue renovation work in both bathrooms and the rear of the church building.

Week 6 (12/14 - 12/18): Complete Bathroom Renovations and Install New Ceiling Lights/Tiles

The Contractor is scheduled to complete renovation work in both bathrooms. The Contractor is also scheduled to install flooring in Pastor's office and new ceiling tiles.